Departmental Report
1976-77
General Manager, Railway and Chief Resident Engineer
KS
K
52.9
LOW
HONG
KONG
香港公共圖書館
ONG KONG PUBLIC LIBRAR
HONG
*
KONG
香港中央
圖書館
CENTRAL
LIBRARY
HONG KONG
ANNUAL DEPARTMENTAL REPORT
BY THE
Ka
GENERAL MANAGER, RAILWAY AND
CHIEF RESIDENT ENGINEER
R. E. GREGORY,
C.Eng., F.I.Mech.E., F.C.I.T., F.P.W.I., J.
FOR THE
RIES
FINANCIAL YEAR 1976
PUBLIC BRAR
S 362.915 (HK) Kow (187%(77)
* 1st April 1976-31st March 1977
EXCHANGE RATES
Where dollars are quoted in this report they are Hong Kong dollars unless otherwise stated. Since 26th November 1974 the value of the Hong Kong dollar has been allowed to fluctuate in terms of other currencies. On 31st December 1976/31st March 1977 the market rate was apprimately HK$4.67/HK$4.64 US$1.
香
-
書
館
HONG KONG PUBLIC LIBRARIE
CL DOH
INTRODUCTION
GENERAL SURVEY
TRAFFIC
•
OPERATIONS
FINANCE
•
CONTENTS
ད
共圖
MECHANICAL AND ELECTRICAL ENGINEERING
CIVIL ENGINEERING
PERSONNEL
TRAINING
SONG
STAFF WELFARE
U.BLIC
APPENDICES
Paragraphs
1 - 3
4 - 30
31 54
65
66
74 - 83
84
95
96
102 - 103
104
107
I - XXVII
HK 35219 Kou
INTRODUCTION
HOUSING NUTUORITY
LORARY
The British Section of the Kowloon-Canton Railway was first opened to traffic on 10th October 1910 after four years of construction. It included a branch line of two feet gauge from Fanling to Sha Tau Kok from 1911 to 1925. The terminal at Tsim Sha Tsui was opened in 1916. Until the removal of Kowloon Station to Hung Hom in November, 1975, the railway ran from Tsim Sha Tsui at the southern tip of Kowloon Peninsula to Lo Wu at the border with China, a distance of 36 milometres (22 miles). The removal of Kowloon Station reduced the distance to 33.51 kilometres (20.82 miles). The system is a single line of standard gauge of 1,435 mm. (4 feet 8 inches) wide with nine stations, including terminii at both ends and a passenger and goods station at Mong Kok. There is a branch line of 1.00 kilometre to Wo Hop Shek near Fanling which is used only on festival days. Work is in progress to convert from a single line to a double track to Sha Tin, the first phase of a plan to double track the line from Hung Hom to Tai Po Market and eventually to Lo iu.
2.
Since the removal of Kowloon Station
to Hung Hom, the number of daily passenger trains has increased from 36 to 44, including trains operating between Hung Hom and Fanling and Tai Po Market. On Sundays and public holidays, additional passenger trains are run to cope with the in- crease in passengers. On certain festivals, such as Ching Ming and Chung Yeung, when large numbers of people are expected to visit the New Territories, special trains are provided to meet the increase in demand. The maximum number of freight trains which can be operated each day is twenty.
3.
Before 1949, it was possible to travel without changing trains from Kowloon to Canton and briefly in 1937 to Hankow. Since then, people travelling to and from China must change trains at Lo Wu. Freight and mail wagons, on the other hand, cross the border without transhipment, except for a change of the locomotive hauling the train. The journey time for a passenger train from Hung Hom to Lo Wu is slightly over an hour, including stops at each of the seven intermediate stations.
4.
ON
GENERAL SURVEY CLIO
The year, which began on a quiet note, turned out to be a difficult one for the railway, with three disruptions to traffic, one lasting one and a half months. As a result of these and the internal situation in China, the revenue for the year showed a decline for the first time in nine years. The last time when revenue dropped was in 1966/ 67 when public transport companies in general suffered a loss in passengers as a result of disorder in Hong Kong. The following table compares the performance of 1976/77 with 1975/76.
20 FEB 1991
UREAN COUNCIL PUBLIC LIBRARIES
Clasa, HK 35219
Author
кош
市政局公共圖書館 UCPL
HKOC (HK)
3 3288 00822600 5
HD LIB)
Chargeable freight tonnage Number of passenger journeys Head of livestock
Goods revenue
Passenger revenue
Gross railway revenue
Recurrent expenditure
1975/76
1976/77
Percentage Increase/Decrease
1,538,958
1,386,865
9.88
13,398,244
12,210,985
8.86
1,811,637
1,641,682
9.38
- 12.40
9.69
-
9.76
$18,092,404 $15,848,346 $17,287,289 $15,612,030 $38,611,025 $34,839,595 $26,916,362 $30,819,476
+ 14.50
5.
Freight tonnage as shown elsewhere in this report is in metric tonnes. Passenger figures are based on the number of tickets sold at stations and on trains. As no charge is made for children three years old and under, the total number of passengers actually carried is greater.
6.
Imports from China, which represented 99.92% of the freight carried, dropped from the previous year's figure of 1,537,697 tonnes to 1,385,815 tonnes. The drop was due mainly to the internal situation and earth quakes around Tang Shan in China, and the subsidence of a bridge at Tai Wai, which severed the railway and isolated the freight unloading yards. Although temporary yards were opened north of the bridge the facilities available were insufficient to cope with the normal freight volume coming from China. The effect of the subsidence deprived the Railway of all unloading facili- ties south of Tai Wai. As a result, the Chinese authorities were forced to transfer some freight to sea transport. Some of these arrangements continued for several months after the bridge was replaced and through traffic resumed in mid October. Export tonnage was 704 tonnes, a decrease of 82 tonnes over the previous year. Freight carried within the New Territories dropped slightly from 475 tonnes in 1975/76 to 346 tonnes.
7.
The number of passengers who travelled wholly within the Hong Kong decreased from 11,868,132 in the previous year to 10,605,010, a decrease of 10.6%. This was due mainly to the removal of Kowloon Station from the busy focal point of Tsim Sha Tsui to Hung Hom and the damage to the bridge at Tai Wai, which occurred during the summer vacation period when large number of school children would have used the railway for travelling to the New Territories. Passengers who travelled to and from China increased by 4.96% from 1,530,112 in the previous year to 1,605,975. The increase is attributed to the recovery of Hong Kong's economy.
8.
Net profit for the year dropped to $4.02 million, 65.8% less than the previous year's profit of $11.74 million. The decline was due to the fall in freight and passenger revenue and a higher operational cost. The higher cost was mainly caused by a revision of salaries and the cost of operating the
new Kowloon Terminal.
9.
Accumulated funds rose from $60.6 million in the previous year to $64.6 million, an increase of 7%. The value of fixed assets at the end of the year was $45.8 million, an increase of 12% over the previous year's figure of $40.8 million.
2
10.
As an extension of the policy to use all available resources to earn revenue, advertising on trains was introduced during the year. The public address system installed in the coaches by an advertising agency was also used to advise passengers when to alight from a train and disseminate official information. The leasing out of the Southern Concourse of the Kowloon Terminal for exhibitions continued during the year and was used by Government and private organisations.
11.
Six power operated ticket printing and issuing machines ordered in the previous year to cope with the expected increase in passengers when the new Race Course station opens and the double track to Shatin is in use arrived at the end of the year and work began in March 1977 to install them in the Booking Office of Kowloon Station. When installed these machines will be able to issue tickets at twice the rate of manually issued pre- printed tickets. The higher issuing rate of these machines is expected to reduce the waiting time in buying tickets at peak travelling periods and on holidays when passenger traffic is particularly heavy.
г.
12.
Work on double tracking the line from Hung Hom to Sha Tin continued during the year and was expected to be complete at the end of 1977. Approval was sought during the year to commence work on the second phase to extend the double tracking to Tai Po Market when the first phase has been completed. Eventually, it is intention to extend the double
tracking to Lo Wu.
JAI
13.
The double tracking of the line is part of a programme to modernize and expand the services of the Railway. With the shift of the population to the New Territories and an expected increase in freight shipments from China, the existing single track will be incapable of meeting future demands. To cope with this, Government has approved expanding the service by adding a second track, which will eliminate many of the limita tions inherent in single track operation and so enable the operation of faster and more efficient train services.
14.
A tender was awarded during the year for installing a colour light signalling system on the double tracked section between Hung Hom and Sha Tin to replace the existing mechanical semaphore system which has become obsolete and incapable of coping adequately with the higher frequency of trains being operated. As double tracking is extended to the north, the mechanical system north of Sha Tin will also be replaced by colour light signals and which will allow a higher frequency of trains to be operated than the existing system can accommodate.
By
15.
As train frequencies and speeds increase the time available for carrying out maintenance work on the track will diminish whereas the rate of wear will increase. To counter this, approval has been given to introduce mechanised maintenance and improve the quality of the track. increasing the depth of ballast, replacing the existing wooden sleepers with concrete sleepers and substituting heavier rails welded into long lengths, it will be possible for a tamping machine to maintain the track in future more rapidly, consistently and economically, and enable rail renewal to take place less frequently.
3
16.
The construction of an oil unloading siding at Fo Tan was 90% complete at the end of the year and it was expected to open in April 1977. It will provide unloading and storage facilities for diesel oil and dry goods coming from China. The yard might also be used for unloading kerosene
and liquid petroleum gas.
17.
The construction of a Marshalling Yard at Lo Wu was well under way during the year and was expected to be completed in early 1978, at which time freight trains currently marshalled in China would be marshalled in Hong Kong. Although it should have been the responsibility of the Kowloon- Canton Railway to marshal freight wagons coming from China, according to their destination and commodities to facilitate unloading, the Chinese had so far undertaken the responsibility because of the lack of such a yard in Hong Kong. In view of the increasing volume of freight destined for Hong Kong, the Chinese authorities had found it difficult to continue this activity and as a result it was necessary to build the marshalling yard. Although the yard should become fully operational in 1978, four sidings will be ready for use in November 1977.
18.
Investigation started during the year on the possibility of building a second tunnel through the Lion Rock at Beacon Hill adjacent to the existing tunnel to enable the double tracking between Hung Hom and Sha Tin to be fully exploited. The new tunnel will have two tracks with more gentle gradients and a lower summit. Whereas it is feasible to improve the existing tunnel, this would cause severe disruption to trains and the work would be prolonged. This effect together with the cost of building an additional single bore tunnel would be similar in overall cost to building the proposed new double tracked tunnel and it was therefore decided to build a second tunnel to replace the existing one.
19.
The construction of a station at the new Race Course in Sha Tin started at the end of the year and is expected to be completed in September, 1978, before the Race Course opens.
20.
Other projects in hand include building a loop line and an additional platform and footbridge at Sheung Shui Station and remodelling Sha Tin and Mong Kok Stations as part of a project to double track and modernize the railway. The latter two stations would be part of a complex including offices, shops and other facilities. Work was expected to com- mence on rebuilding them in late 1977.
21.
Consultants from Transmark (Transportation Systems and Market Research Ltd.), a British Railways' subsidiary arrived at the end of 1976 to carry out a study into the modernization and expansion proposals of the Railway and in particular to recommend the most efficient type of traction system, the type of rolling stock which would be necessary, and examine the viability of the following proposed additional lines :
Kowloon Station at Hung Hom to Tsim Sha Tsui;
Tai Wai to the Kwai Chung Container Terminal;
Tai Po Market to the Tai Po Industrial Estate and Shuen Wan;
4
from Sheung Shui to Tuen Mun;
a duplicate route from Kowloon to Sha Tin.
The study was expected to be completed in September, 1977, and a full report of the findings, together with the recommendations presented to Government before the end of 1977.
22.
Two new locomotives of 2,000 horse power and a spare locomotive bogie ordered from the General Motors Corporation of the United States of America in the previous year arrived in March. The two locomotives were designed for fast acceleration and multiple unit operation. They have larger fuel tanks and a more comfortable cab. The spare bogie was to help to in- crease the availability of locomotives by reducing the time a locomotive was out of use due to defective bogie.
23.
Air conditioning was installed in four first-class coaches during the year and entered service in February, 1977. A supplementary fare of $1.00 is charged for a journey irrespective of the distance travelled. It is intended to convert another four in the 1977/78 financial year to help fully test the commercial attractiveness of air conditioning by enabling each train to have an air conditioned coach.
24.
To help prevent passengers from boarding a train at the last moment with a possible risk of accident, train departure signals were in- troduced at Mong Kok and Fanling Stations in October, 1976 on an experimental basis. Thirty seconds before a train departs a series of bleeps are sounded over the public address system to warn passengers of the impending departure of the train. If the system proves successful, it will be extended to other stations.
25.
In order to implement new investment more efficiently and improve the proficiency of management, several new posts were submitted to the Government Secretariat for approval. The object is to enhance pro- fessional ability and personal accountability and provide a level of manage- ment more removed from involvement in the day-to-day control of railway operations so that greater attention can be given to planning and policy formulation.
C
26.
The Government has agreed to two posts of Assistant General Manager, a Training Manager, Marketing Officer, Project Manager and Development Engineer. Further posts of Assistant General Manager (Technical) and Senior (Civil) Engineer are under consideration. An Assistant Depart- mental Secretary was also provided, on a temporary basis, to assist in the increasing volume of personnel matters.
27.
The structure of the railway grades needs modification to suit the expected modernization of the railway, to improve versatility and remove some anomalies between grades due to changing work loads and wage inequities. Proposals have been submitted to the Government Secretariat and these will be discussed with the Trades Union before implementation.
5
28.
The revision of the railway Standing Orders (Railway Rule Book) which started in 1974 was completed and forwarded to the Government Printer for printing at the close of the year. The Book was last revised in 1946 and had remained virtually unchanged. The new Book will be printed with loose leaves to facilitate the inclusion of future amendments.
29.
1
The Railway suffered a major disruption during the year when the bridge over Shing Mun River, between Tai Wai and Sha Tin, was under- mined by a rainstorm at the end of August. As a result it had to be de- molished and rebuilt. During this period, which lasted from 25th August, 1976 to 11th October, 1976, a shuttle train service was operated either side of the river with a bus link operated by the China Motor Bus Company connecting the rail services. Some 12,500 people were carried each day. Freight traffic suffered considerably because of the lack of freight terminii all of which were located south of the bridge and as a temporary expedient. sidings in the Workshops at Ho Tung Lau, the branch line to Wo Hop Shek and the section of the main line between Sha Tin Station and the Shing Mun River, together with the partially completed oil unloading yard under construction at Fo Tan, were brought into use as temporary unloading yards. With these measures, it was possible to continue to receive freight traffic from China, although the volume was restricted. Possibly because of this the price of some food stuffs rose on the local markets. The disruption demonstrated the importance of the Railway for the transportation of commodities from China. Additionally the China Travel Service (Hong Kong) Ltd. constructed oil unloading facilities on the sea wall adjacent to the main line at Pak Shek Kok between Tai Po Kau and University Stations.
30.
Apart from this disruption, the Railway suffered two further disruptions at the close of the year. On 4th March, 1977, the railbus was derailed near Ho Tung Lau Workshops due to the collapse of scaffolding on adjacent road works, blocking traffic through the area for a few hours. On 20th March, 1977, six wagons of a train of empty wagons returning to the Chinese Section were derailed at Keng Hau, outside the northern portal of Beacon Hill Tunnel necessitating closing this section of the line for one day to enable repair work to be carried out. The track had recently been slued after a span of bridge No. 9 had been moved to facilitate the provision of an additional span as part of the double tracking project.
TRAFFIC
31.
Traffic earnings decreased by $3,919,318 (11.08%) in comparison with the previous year. Recent trends are shown below :
1973/74
$21,996,433
1974/75
$28,688,809
1975/76
$35,379,694
1976/77
$31,460,376
32.
On 22nd April 1976, the Chief Secretary, Sir Denys Roberts visited the Ho Tung Lau Workshops in the company of the General Manager.
6
33.
On 10th May, 1976 and 23rd May, 1976, Prime Minister LEE Kuan- yew of Singapore went to and returned from China by rail respectively.
34.
Passenger Traffic Local passenger journeys decreased by 10.64% but international journeys increased by 4.96%. In the case of the former, the decrease is largely attributed to the new location of the Kowloon Terminal with poor connecting public transport facilities, the increase in fares, collapse of Railway Bridge No. 11 at Tai Wai and the exceptionally cold weather. The increase in journeys to China relates to the larger number of Hong Kong residents visiting relatives and friends in China.
35.
On Sunday, 4th April, 1976, the Ching Ming Festival and Monday, 5th April, 1976, 29 and 25 special trains were operated in addition to the normal daily train services and 118,638 and 64,584 passengers were carried respectively. The majority went to the Wo Hop Shek and Sandy Ridge Cemeteries.
36.
On 2nd June, 1976, the Dragon Boat Festival, 10 special trains were run to and from the New Territories to enable the passengers to see the Dragon Boat Race held at Tai Po (Yuen Chau Tsai). Altogether 21,695 passengers were conveyed to all stations.
37.
On 25th August, 1976, following a severe rainstorm, landslides were reported between University and Tai Po Kau, and Sha Tin and University at 05.15 hours and as a result, a shuttle service was initiated between Kowloon and Sha Tin and Tai Po Kau and Lo "u. The latter was extended to Sha Tin at 12.10 hours. At 08.45 hours, a deformity to the arches support- ing the bridge over the Shing Mun River just north of Tai Wai was dis- covered and the shuttle service between Kowloon and Sha Tin was suspended. The deformity was such that it was found necessary to demolish and rebuild the bridge.
38.
From 26th August to 11th October, 1976, shuttle train services were operated on both sides of the Shing Mun River. In the north, the service ran from Sha Tin to Lo Wu. In the south, the service initially ran from Hung Hom to Mong Kok, but a few days later was extended to Tai Wai where a temporary station was built in forty eight hours for this service. From 1st September, 1976, a bus link was provided to transfer passengers between the two sections of the railway at no extra charge. This service remained in force until through traffic was resumed on 11th October after the construction of a new permanent single span. A further span is to be added in 1977.
39.
On Sunday, 31st October, 1976, the Chung Yeung Festival Day and Monday, 1st November, 1976, in addition to the normal service, 27 and 23 special trains were operated respectively and 86,554 and 39,505 Passengers were carried. The majority were worshippers who went to Wo Hop Shek and Sandy Ridge Cemeteries.
40.
On 20th February, 1977, the Third Day in the First Moon of the lunar calendar, a total of 85,611 passengers were conveyed to all stations. On 16th Febraury, 1977, the Day before the Chinese New Year Eve, a total of 19,425 passengers were conveyed to Lo Wu, a new record.
7
41.
New lavatories at Fanling and Tai Po Market stations were opened to the public for use on 28th October, 1976 and 13th February, 1977 res-
pectively.
42.
Four air-conditioned carriages were put into service on 7th February, 1977.
43.
Fares and Rates From 2nd July, 1976 to 31st August, 1976 (except Sundays and Public Holidays) special half-fare student tickets were issued for train journeys between Kowloon and Mong Kok to New Territories stations. Altogether 11,502 tickets were sold compared with 19,652 the previous year. Less tickets were sold because of inclement weather and the damage to Bridge No. 11.
44.
The supplementary fare for travelling in an air-conditioned first class carriage is 1.00 irrespective of the distance travelled.
45.
Freight traffic New goods sidings at Ho Man Tin were put into service on 17th May, 1976. They are capable of handling more than 40 live- stock wagons at a time. The goods yard at Mong Kok will be demolished for re-construction by October, 1977 and all livestock wagons will then have been transferred to Ho Man Tin Sidings. The new sidings will increase live-stock handling capacity and speed up unloading. This has the benefit of reducing the rate of mortality and the extent of offensive odour caused by the loaded wagons standing in the sun for lengthy periods. In order to provide more space to speed up freight unloading at the Goods Yard in Hung Hom, the areas between sidings were paved and some sidings removed. This project started in December 1976 and is expected to be completed in October 1977. After completion, it will increase the number of unloading places from 91 to 106.
46.
The construction of a lorry holding area at the entrance to the Goods Yard at Hung Hom Terminal started in January 1977. Its provision is to avoid traffic congestion caused by lorries parked along the Salisbury Road extension awaiting entry into the goods yard. It can accommodate up to 50 lorries and is expected to be completed in July 1977.
47.
During the collapse of Railway Bridge No. 11 at Tai Wai, mail and general cargo were dealt with at the sidings of Fanling Station, Fo Tan Yard, Ho Tung Lau Workshops and part of the main line on either side. of Mile 7 level crossing. Livestock wagons were mainly dealt with at Wo Hop Shek. Temporary measures were undertaken to unload diesel oil onto barges near Pak Shek Kok south of Tai Po Kau Railway Station after the close of daily passenger traffic. With the co-operation of the Chinese railway authorities and the local consignees, the effect on the inward goods from China during the period was minimized.
48.
The decrease in freight revenue is attributed to the decrease in goods from China. Comparative figure for goods revenue as follows :-
8
Increase/
1975/76
1976/77
Decrease
Carriage of general merchandise
$14,563,608
$12,608,951
-$1,954,657
Tonnes
Other freight ser-
(1,538,958) (1,386,865) (- 152,093)
vices, Handling
charges, baggage,
parcels, etc.
Total freight
revenue
Percentage
Increase/
Decrease
- 13.42
(- 9.88)
$3.528.796 $3.239.395 -$ 289,401 $18,092,404
-$2,244,058
-
8.20
$15,848,346
- 12.40
49.
The following principal commodities imported by rail into Hong Kong during the year, amounting to 49.29% of the total tonnage, were :-
Apples .. Steel Bars
Beer
Cardboard
Cement ...
•
Cotton piece goods
Eggs
Cotton, raw
•
Meat frozen.
Oil,
diesel
Onions
Oranges
Paper
Pears
Vegetables, fresh
7,372 tonnes 14,262
#t
20,586
"
7,642
11
31,281
32,303
#1
15,770
11
37,529
11
23,350
11
158,528
#
5,349
#1
4,854"
13,522
曾
14,047
11
9.485
"
395.880
50.
Additionally, the head of livestock conveyed for the same
period was 1,641,682 including 1,591,742 pigs.
51.
A total of 5,964 cold storage wagons conveying 113,356 tonnes of frozen goods were received from China including :-
No. of wagons
1,779 132
883
Description of goods
Tonnes
Eggs Fresh fruits beat
27,749
1,965
13,350
New refrigerated wagons are being introduced with a net capacity of 40 tonnes compared with 30 tonnes in the older wagons.
9
52.
Other cold or frozen goods included poultry, vegetables, fish,
prawns, chestnuts, preserved meat, milk and ice cream.
53.
Mail and mail packets amounting to 4,940 tonnes compared with 5,874 tonnes in the preceding year, were conveyed by rail to China. The amount was distributed evenly over the whole period under review except a seasonal peak of 714 tonnes in January which reflected the approach of the Chinese New Year.
54.
Full details relating to goods traffic are shown in Appendix XI.
OPERATIONS
55.
After the introduction of the new timetable on 30th November, 1975, the incidence of passenger trains arriving less than five minutes' late reached 92.82% compared with 78.56% of the preceding year. The centage of trains arriving at their destination on time was 77.96 com- pared with 44.84 of the preceding year.
H
per-
No. of scheduled
Passenger trains
Percentage
Trains on time
11,218
77.96
Trains delayed for less than 5 minutes
2,139
14.86
Trains delayed for more
م
than 5 minutes
1.033
7.18
Total No. of passenger
trains run
14,390
100.00
56.
The number of freight trains were 2,098 from China and 1,956 to China, the latter were virtually empty.
57.
The number and types of special trains run during the year were as follows :-
Up
Down
Total
Passenger Passenger (empty)
Ballast
221
220
441
106
106
51
51
102
Total :
272
377
649
58.
On 30th October, 1976, train departure signals were introduced
at Mong Kok and Fanling Railway Stations.
10
59.
On 6th December, 1976, a public address system was introduced into all coaches which provided music, advertisements and enabled announce- ments to be made by the Guard to all passengers.
60.
On 4th March, 1977, the railbus was derailed at 05.04 hours about 200 feet north of Railway Mile 9 level crossing. Shuttle train services between Lo Wu and University and Kowloon and Sha Tin were intro- duced up to 09.00 hours when through traffic was resumed.
61.
On 13th March, 1977, Bridge No. 9 was moved to the east in order to provide sufficient space for laying a second track as part of double tracking from Kowloon to Sha Tin. Shuttle train services were provided between Sha Tin and Lo Wu. A substitute bus service was introduced between Sha Tin and Kowloon.
62.
On 11th March, 1977 two new locomotives arrived from the U.S.A. and were put into service on 14th March, 1977.
63.
On 20th March, 1977, an empty goods train was derailed in the vicinity of Railway Bridge No. 9 at 06.24 hours. Shuttle train services between Sha Tin and Lo Wu were put into service for the whole day. On 21st March, 1977, shuttle train services between Sha Tin and Lo Wu and between Kowloon and Mong Kok were put into service with buses from the Kowloon Motor Bus Co. Ltd. operating a connecting service between Sha Tin and Mong Kok up to 16.00 hours, when through traffic was resumed.
64.
Accidents during the year:
Trespassers injured by trains Trespassers killed by trains Passengers injured by trains
Passengers killed by trains Staff injured on duty
Derailments:
D
(a) Chinese Section goods wagons
(b) Rail-bus
(c) Passenger coaches
(d) Locomotives
Collisions :
1975/76
1976/77
4
8
18
2
7
LIBRARI
14
7
754 TE
(a) Passenger coach with buffer
stop
(b) Passenger train with a lorry (c) Brake van with buffer stop (d) Goods train with buffer stop (e) Between pick-up wagons
11
2
2
1
1
1
1
1
1
2
1
LIIN-
65.
During the year an extensive publicity campaign was introduced to advise the public to avoid exposing themselves to danger when on the railway and new posters were exhibited at all stations. Additionally the availability of the public address system in all coaches enabled the Guard to warn passengers not to travel in dangerous locations. The introduction of a departure signal at stations was a further effort to improve public awareness of the need for greater safety.
FINANCE
66.
Operating expenditure increased by 15.1% from $23,298,218 to $26,825,806 due mainly to the increase in salaries for the additional staff for the new railway terminal at Hung Hom, a revision of salaries and the continuing escalation in the cost of materials. The gross operating profit fell from $12,221,977 to $4,693, 646 whilst the net profit was $4,020,119 compared with $11,740,288 in the previous year. Accumulated Funds, excluding interest, rose to $64,624,443 at the end of the year.
67.
68.
The decrease in net profit was due mainly to :
(a)
a general decrease in the numbers of passengers and volume of freight traffic especially during the suspension of railway traffic between 25th August and 10th October, 1976 caused by the
subsidence of the railway bridge over the Shing Mun River.
(b) generally less imports from China especially of diesel
oil.
(c) higher cost of maintaining the terminus at Hung Hom.
During the year, additions to fixed assets totalled $8,297,662. The major increases included the acquisition of two new diesel electric locomotives and one landrover, capital expenditure included associated emer gency work for bridge No. 11, improvement to Lo Wu Station and various improvements to existing facilities such as air-conditioning of four coaches and equipment for the maintenance of track.
69.
The accounts and supporting data are published in Appendices I to VIII in this report.
70.
The Operating Ratio, which consists of the percentage of operating expenditure to revenue rose from 65.59 to 85.11 largely due to the decline in revenue of $4 million and the increased Kowloon terminal cost of HK$1.68 million arising from the transfer from Tsim Sha Tsui to Hung Hom. The profit of HK$4.0 million may be regarded as satisfactory in view of the year events.
12
71.
Freight income at $15.848 million continued to be slightly higher than passenger revenue while the proportion of non traffic revenue rose to 9.7%. The value of net fixed assets rose by $5.0 million and the return on capital fell to 10.25% from the exceptionally high figure of 29.98% in the previous year.
72.
A Business Statement is included as appendix V. Its purpose is to identify the more avoidable expenditure as distinct from costs which are wholly joint and generally invariable. From this the dependence of the railway on freight traffic can be seen with goods revenue contributing $13.47 million to joint costs against a passenger contribution of only $1.72 million. The Statement is part of a management information system aimed at developing profit and cost centres as an aid to identifying the performance of individual managers and to help in formulating commercial policy.
73.
Appendix IV further analyses the passenger business and shows that of the total passenger revenue of $15.612 million, 20.17% relates to international traffic with the People's Republic of China and 67.37% to passengers travelling wholly within Hong Kong originating or terminating their journeys north of Shatin. This demonstrates the advantage in encoura- ging longer journeys. The development of Shatin as a new town will un- doubtedly increase the usage of the railway but growth in the Tai Po and Sheung Shui areas and increased travel to and from China will give the railway a greater financial benefit which, moreover, relates to a market less affected by road competition.
74.
MECHANICAL AND ELECTRICAL ENGINEERING
All locomotives, rolling stock, electrical and mechanical equip ment, machinery and plant were maintained to a good standard during the year, especially during the interruption to train services due to the damage to Bridge No. 11 on 25th August, 1976. within the period between the accident and up to the resumption of service on 11th October, 96, there were only four locomotives north of the bridge, but there were no failures which testified to the high standard of maintenance. Also during this period, the Railway Workshops made sidings available for unloading food stuff and other commodities from China. In order to enable unloading to be undertaken after sunset and at other emergency yards during this period, temporary lights were installed for the temporary yards at Sha Tin, Fo Tan and Tai Po Kau. The Workshops Section also played an active part in conjunction with other Sections in developing and implementing a number of projects.
75.
A comprehensive Work Study exercise conducted by Organisation and Methods Division of the Finance Branch, Government Secretariat, on be- half of the railway was carried out at the Workshops at Ho Tung Lau in the later part of the year. Recommendations including improvements in and an increase of supervision were made. The report is being studied by the Management to analyse the feasibility of implementing the recommendations.
76.
Locomotives The availability factor of diesel locomotives was 87.9% compared with 91.3% in the previous year. The comparatively lower availability was due to a greater incident of locomotive overhauls during the past year.
When the railway was severed due to the need to reconstruct
13
bridge No. 11, in order to sustain a high level of locomotive utilization, tem- porary arrangements were made to perform all examinations and servicing at night. Maintenance cost rose from $1.386 per km. in the previous year to $1.684 per km. The increase was the result of the increased cost of spare parts due to inflation. To cope with the increasing volume of passenger and freight traffic, two more locomotives and one spare locomotive bogie ordered the previous year arrived in Hong Kong on 11th March, 1977. After passing through commissioning tests and track runs, the two locomotives were released to service on 14th March, 1977.
77.
The average consumption of diesel oil was 3.74 kg. per engine km. compared with 3.52 kg. per engine km. in the previous year, reflecting the heavier weight of trains. The total average cost of maintenance and oil con- sumption per locomotive km. was $4.07 compared with $3.72 in the previous year.
78.
Carriages and wagons Availability of carriages was 89.93% com- pared with 88.13% in the previous year and the maintenance cost per passenger coach km. $0.331 compared with $0.305 in 1975/76. Again the higher mainten- ance cost was mainly the result of inflation. Four first class passenger carriages were equipped with air conditioning and released into service on 7th February, 1977. Two spare passenger carriage bogies ordered from Japan last year arrived on 3rd February, 1977. Two more covered wagons were con- verted into brake vans for the Traffic Section. A public address system on trains and advertisements in carriages were introduced in this year. Modi- fication of 40 Japanese coach alternators was completed early in the year increasing output from 70 to 95 amperes.
79.
Plant and Equipment In order to cope with the increase in work load in the Workshops, minor improvements, including the construction of a spray painting room, sand blasting room and cleaning pit were started and should be completed in the year 1977/78.
80.
An order was placed last year for a new wheel lathe from the United Kingdom to replace the existing lathe which had reached the end of its useful life and was beyond economic repair. The new lathe which has a higher turning speed will enable wheels to be profiled in about one-eight the time of the existing lathe. As the number of trains increases, wheels will wear at a higher rate and need re-profiling with higher frequency in order not to endanger the safety of trains. The wheel lathe was scheduled to be delivered in 1976, but delivery was delayed to 1977/78. Because of the introduction of the metric system, one of the existing lathes was converted from imperial to metric sizes and a new metric lathe was ordered for delivery by the middle of 1977.
81.
Additional electric lights were installed by the Workshops at Lo Wu as part of the station improvement, Tai Po Kau passenger waiting shelter, Hung Hom Lorry Holding Area and Fo Tan Goods Yard. Under the supervision of a service engineer from the Westinghouse Brake & Signal Co. of the United Kingdom, the Workshops Section Provided assistance in the installation of a signalling system at Fo Tan sidings. This project was expected to be com- pleted in early 1977/78. Building services items within railway premises, plant and equipment were maintained to a good standard during the year.
Work done for other Government Departments included manufacturing
82.
14
2,000 letre hot water cylinders, and various castings of iron, bronze and aluminium, etc. Additionally the workshops also manufactured railway switches
and turnouts.
83.
Statistical statements relating to analyses of train and locomotive running, fuel oil expenses, consumption of lubricants and the cost of repairing locomotives, carriages and wagons will be found in Appendices XII to XV while the classification of rolling stock is shown in Appendices XVI to XX.
84.
CIVIL ENGINEERING
The first supply of the heavier UIC 54 rail (54 kilogrammes per metre) was delivered at the end of 1976 and a contract let for the production of concrete sleepers. It was expected that delivery of these would start in May, 1977.
85.
Two teams of welders were trained during March by a representative from Thermit Welding (GB) Ltd. and a start made on track welding. Initially welding was confined to platform lines at Hung Hom Terminus, and then proceed- ed to the new up line between Mong Kok and Kowloon Tong where track was welded into 108 feet lengths. The new oil siding at Fo Tan was welded into long lengths and although laid with the older 95 lb. rail, with concrete sleepers it was the first section of track of modern construction and will be the standard in future.
86.
Authority was received during the year to reballast the whole of the railway to a greater depth over a period of five years in conjunction with the adoption of heavier track. The commencement of this work was delayed due to difficulties with the acquisition of land and delays in the completion of the double tracking project, but is hoped that the work will start during mid-1977.
87.
A submission was made for supplementary provision under the track reballasting programme for the premature renewal of one mile of track each year in conjunction with the ballasting work, to enable the existing track to be raised to a higher standard before full double tracking is introduced.
PID
88.
Authority had been received for the purchase of an ultra-sonic rail testing machine which will be purchased in 1977/78 and two members of the staff will be trained to operate it. This will enable cracks in rails to be detected before they become visible to the naked eye and so increase the safety of the railway and reduce traffic delays.
89.
The increased frequency of traffic makes the time available for track maintenance during the day limited and the periods for possession during the night are reduced. This reduces the efficiency of track mainten- ance work and the increased traffic causes heavier wear. Authority will be sought to obtain a tamping machine for packing and lining the track. This will become more important when the heavier track is extensively in use.
90.
Following the derailment near bridge No. 9 on 20th March, 1977, it was agreed that in future all permanent way work involved in new projects and affecting running lines would be carried out by K.C.R. staff and
15
URBAN COUNCIL PUBLIC LIBRARIES
REFERENCE LIBRARY
an application will be made to increase the staff for this purpose.
91.
In connection with the development of Sha Tin New Town, civil engineering works were carried out adjacent to, over, and under the railway at a number of locations in Sha Tin. Close liaison was maintained with the consulting engineers, Maunsell Consultants (Asia) Ltd. regarding safety measures to be taken to safeguard the railway. On 4th March 1977 at about 5.08 hours the formwork for the construction of an abutment of an overhead Road Bridge No. 2 collapsed and obstructed the railway near Level Crossing Mile 9 while a railbus approached the section. It caused derailment and damaged the railbus. Train services between University and Sha Tin Railway Stations could not commence until 9.10 hours when the railbus had been re- moved from the site.
92.
Close liaison was also maintained with the Mass Transit Railway Corporation's engineers regarding safety measures to be taken for the cons- truction of H.T.R.C. tunnels underneath the railway at Kowloon Tong.
93.
New Works and Improvements
EC
Site formation work for the construction of the Marshalling Yard at Lo Wu started. Excavated materials were transported from Hong Lok Yuen Borrow area to the filling area at Lo Wu. Up to the end of March, 1977, some 142,000 cu. yd. of filling had been dumped.
Construction work for Fo Tan Oil Sidings was carried out and the oil track was substantially completed while the dry goods track and yard building construction was in progress at the end of the year.
A new platform shelter was erected at Tai Po Kau Station.
Two new latrines were constructed at Tai Po Market and Fanling Stations by the Public Works Department. Two new latrines at Tai Po Kau and University were under construction at the end of the years
Fifteen new platform benches were constructed at Lo Wu Station; the old 3rd class restaurant was demolished and reconstructed as a Store room, the toilets in the 1st class waiting hall were reconstructed and enlarged.
A lorry holding area adjacent to Kowloon Station was under construction at the end of the year.
The windows facing the mainline in the Erecting and Painting Shops at Ho Tung Lau Workshops were protected with wire mesh. As an improvement to the Railway Workshops, the following items were constructed :
washing pit 85 feet long; sand blasting room; and
spray painting room.
16
!
94.
Typhoon and Rainstorm Damages
As the result of typhoon and rainstorm during the year, the following remedial works were carried out :-
95.
The slope at the back of Luen Wan Street was resurfaced with chunnam.
Bridge No. 11 was reconstructed by the Railway Division of the P.W.D.
Staff quarters at Sheung Shui and Sha Tin were repaired.
Minor damage to windows and doors of gang huts, staff quarters etc. were made good.
Works undertaken for outside parties
Resiting oil pipes at Hung Hom for the P.W.D.
Laying sewers under one turnout and two tracks at Hung Hom for the Chief Engineer Railways P.W.D.
at
Laying cable ducts under the track at Mile 7 and Tai Wai for the China Light & Power Company.
Laying 12-way cable ducts under the track at Mile 7 for the Hong Kong Telephone Co.
ए
Others items of minor civil engineering work can be found in Appendix XXI.
PERSONNEL
RAR
96.
In the period 1st April 1974 to 31st March 1977 the railway establishment increased from 828 to 1005. An increase of 93% over last
year's establishment of 986. The major increases occurred in the Traffic Section and the Workshops Section where labouring and aritsan staff in- creased by 40%.
Planning and Administration Division
Addition
1 Assistant General Manager
Engineer (Project Manager)
1
1
Senior Engineer (Super-
numerary)
1
Senior Railway Officer
(Training Manager)
1
Typist
Planning and Administration
Project Management
Liaison with consultants undertaking study on moderniza- tion of K.C.R.
Improvement in job performance
of staff
17
Deletion
1
Assistant General Manager (Supernumerary)
Replaced by permanent post
Traffic Division
Addition
1
Assistant General Manager
1
Chief Railway Officer
(Operating Manager)
1
Senior Railway Officer
(Terminals Manager)
1
Senior Railway Officer (Marketing Officer)
Deletion
1
Traffic Controller
Assistant Traffic Controllers
Way and Works Section
Administration and management
of Traffic Division
Train operation
Terminals and stations operation
Marketing and public relations
Replaced by 1 post each of A.G.M., C.R.0. and S.R.O.
པ
Addition
1
Engineer/Assistant Engineer
Assistant Inspector
1
1
Foreman
1 Foreman (Supernumerary)
22
2
2
4
Artisans I
Artisans I (Supernumerary)
Way & Works Trainees
Workshops Section
Development of civil engineering projects
Welding rails
с
Trainee Platelayers
Addition
1 Electrical Engineer/Assistant
Electrical Engineer
Maintenance of colour light signalling and electrical aspects of plant
Deletion
2
Railway Attendants (Supernumerary)
5
Artisans I (Supernumerary)
18
3
2
2
Artisans II (Supernumerary)
Semi-skilled Labourers (Supernumerary)
Labourers (Supernumerary)
A
97.
Previously the organisation of the Department was divided into various sections. With the creation of the two Assistant General Manager posts, the Department had been re-divided into three divisions: Planning and Administration Division, Traffic Division, and Technical Division. post of Assistant General Manager (Technical) was under consideration at the end of the year and is expected to be approved in the following year. When this extra post is approved, the three Divisions will be headed by an officer of Assistant General Manager level.
98.
Continued efforts were made during the year to improve manage- ment-and-staff consultation. Meetings with the Railway Traffic Officers' Association and Railway Workers' Union continued on a regular basis. Meetings are now held with Divisional heads and only in the case of dis- agreement on matters which cannot be resolved at those levels are items referred to meetings between the General Manager and the union representa- tives.
99.
Mr. R.E. Gregory, General Manager, visited China from 25th April, 1976 to 9th May, 1976 to discuss with the Chinese railway authorities in Peking matters concerning traffic interchange arrangements and future developments. He went on home leave from 15th July, 1976 to 30th August, 1976 and was again away from Hong Kong for a short while during the Christmas and New Yar period. During these periods, visits were made to the Crown Agents, British Railways and suppliers concerned with Kowloon-Canton Railway projects. During his absence on these occasions, Mr. U.L. Wong, Acting Assistant General Manager, acted in his place as General Manager.
100.
During the year a total of 18 officers retired from the service, among them were Mr. LAI Shu-yan, Assistant Way & Works Engineer and Mr. LAM King-kai, Senior Clerical Officer. Mr. I. Agafuroff, ISO, Treasury Account- ant, also left the service after spending 10 years with the Railway.
101.
+
PIT
Officers who joined the department during the year included Mr. Sunny CHOI Shun-shing, who became the first Project Manager of the Department, Mr. WOO Chor-kei, who replaced Mr. I. Agafuroff, ISO, as Treasury Accountant, and Mr. Raymond KAN Pak-chung, who was transferred to the Department from Home Affairs Department as Assistant Departmental Secretary.
TRAINING
102.
Training continued to be promoted at all levels. Staff sent on various training courses during the year included the following :
19
103.
Local Courses
Mr. M.R. Elvy, Way & Works Engineer, attended a Problem Analysis and Decision Making Seminar
Mr. LEUNG Chun-chung, Way & Works Inspector, attended an Introduction to Management Course.
Mr. LI Siu-hop, Assistant Way & Works Inspector, attended a Cantonese Supervisory Course.
Mr. LIANG Min-chung, Senior Clerical Officer, attended a Supervisory Development Course for Clerical Officers.
Overseas Course
Mr. CHOI Yat-how, Traffic Controller, was sent to England to attend a Senior Transport Management Course with British Transport Staff College in Woking from 2nd May, 1976 to 24th July, 1976. He also visited British Railways, London Transport and the Japanese National Railway to study at first hand the techniques used by more advanced Railways in handling the rapid transit of large numbers of passengers. T
Apart from these, a large number of junior supervisory staff
part in both the Way & Works and the Workshops Section attended various acci- dent prevention and industrial safety courses organized by the Labour Department.
STAFF WELFARE
ARIES
104.
Membership of the Credit Union of the Railwa Workshops stood at 73 and outstanding loans amounting to $7,698.62 at
year.
105.
P1976,
close of the
Up to 31st March, 1976, the grant made available by Government for welfare purposes amounted to $23,016.40. Of this amount, $16,676.50 was set aside for interest-free relief loans to officers with monthly salaries not exceeding $2,750 and the balance of $6,339.90 was made availa- ble as grants to assist departmental clubs and associations.
106.
The Railway Sports and Recreation Club organized several week- end launch picnics at a nominal price to various scenic spots in Kowloon and the New Territories during the year. Over 500 staff and family mem- bers joined these outings. In addition, the club also organized buffet and dinner gatherings during Christmas and after Chinese New Year. These dinner were well supported by all levels of the staff.
20
107.
The Workshops Canteen at Ho Tung Lau continued to be well
patronized by the staff of these shops.
R. E. GREGORY GENERAL MANAGER, RAILWAY
AND CHIEF RESIDENT ENGINEER
香港公共圖書
館
NG KONG PUBLIC LIBRAR
21
SUMMARY OF FINANCIAL RESULTS FOR THE PAST THREE YEARS
APPENDIX I
Head
No.
1974-1975
1975-1976
1976-1977
1.
Route Kilometrage-Operated
2.
Gross Railway Receipts
3.
Railway Operating Revenue
....
36
$30,723,929
34
34
$38,611,025
$34,839,595
$28,879,515
$35,520,195
$31,519,452
4.
Railway Operating Expenditure
$21,899,558
$23,298,218
$26,825,806
5.
Nett Operating Revenue
$ 6,979,957
$12,221,977
$ 4,693,646
6.
Percentage of Railway Operating Expenditure to Railway
Operating Revenue
....
75.83
65.59
85.11
7.
Net fixed assets
$39,079,321
$40,772,760
$45,776,073
8.
9.
10.
Percentage of Nett Operating Revenue to net fixed assets Railway Operating Revenue per Route Kilometre Operated Railway Operating Expenditure per Route Kilometre Operated
17.86
802,209
29.98
$1,044,712
10.25
$
927,043
608,321
$
685,242
$
11.
Passenger Receipts
$15,138,697
$17,287,289
12.
Percentage of Passenger Receipts to Gross Railway Receipts
49.27
44.77
788,994
$15,612,030
44.81
13.
Number of Passenger Journeys
13,901,333
13,398,244
12,210,985
14.
Goods Receipts
....
$13,550,112
$18,092,404
$15,848,346
P
15.
Percentage of Goods Receipts to Gross Railway Receipts
16.
Tons of Goods Hauled
44.11
1,167,292
46.86
1,538,958
45.49
1,386,865
17.
Revenue from other sources
Rentals
Incidentals
Central Mechanical
Workshops Services
Advertising
Sales of Surplus and
Condemned Stores
18.
$
$
1974-75 1975-76 1976-77 $1,186,252 $1,976,529 $1,897,960 34,094 $ 63,887 $ 32,802
190,706 $ 140,502 $ 59,076 623,533 $1,049,990 $1,388,365|
535 $
424 $ 1,016 $ 2,035,120
$ 3,231,332
$ 3,379,219
Percentage of Revenue from other sources to Gross
Railway Receipts
6.62
8.37
9.70
L
Expenditure
Traffic Expenses
Traffic Running Expenses
Traffic Salaries and General
Operating
Kowloon-Canton Railway
Account for the year ended 31st March, 1977
APPENDIX II
1976/77
1975/76
Revenue
1976/77
1975/76
4,489,145
4,402,458
Passenger Services Goods Services
15,612,030
17,287,289
15,848,346
18,092,404
6,686,530 11,175,675
5,340,675 |
10,243,133
Morkshop Services
59,076
31,519,452
140,502
35,520,195
Expenses
Maintenance
Mechanical
6,219,881
Way and structures
6,672,463
Rainstorm damage & other emergency repairs
12,892,344
69,442
5,014,485
5.247,084
10,261,569
116,568
Depreciation
Plant
Rolling Stock
Other
Gross Operating Profit C/F
92,807
1,831,239
89,966
1,832,544
764,299 2,688,345
754,438
2,676,948
26,825,806
23,298,218
4,693,646
12,221,977
Expenditure
31,519,452
1976/77
35,520,195
Profit & Loss Account for the year ended 31st March, 1977
1975/76
Revenue
共
CO
Administrative and General
Expenses and Salries
1,269,129
Contribution in lieu of Rates and Duty
1,541,859
Rent
820,000
1,063,011
1,619,101
820,000
Net loss on disposal of Fixed Assets
243,401
Stores Charges
119,281
Net Profit C/F to Balance Sheet
3,993,670
4,020,119
116,032
Rents and Incidental Revenue
Proceeds of Sales of
ARIES
3,618,144
Surplus Stores
Net Profit on disposal of
Fixed Assets
Gross Operating Profit B/F
11.740,288
8,013,789
15,358,432
31,519,452
35,520,195
1976/77
1975/76
4,693,646
3
12,221,977
3,319,127
3,090,406
1,016
424
3,320,143
45,625
3,136,455
8,013,789
15,358,432
Notes on the Operating and Profit & Loss Accounts
The Kowloon-Canton Railway is owned by the Hong Kong Government whose policy is to avoid cash transactions between its departments. However, the Railway prepares its annual accounts based on commercial principles for the determination of its profitability and as a reflection of the performance of management. In these circumstances the market value of all services rendered to Government departments, the renting to them of railway property and the loss of revenue caused by Government action are included in such accounts. A principal item is the considerable difference between actual income derived from the sale of tickets to students and the amount which they would have paid if normal fares were charged and is in effect a sub- sidy to students. The situation is the same as in the case of the bus and tramways companies which are compensated for the concessionary fares charged to students by the payment by Government.
In order that the Railway accounts can reflect income which is part of the normal revenue of non-government owned railways the following notional credits were included in these accounts :
:
Subsidy for Scholar Tickets
Value of tickets issued free of charge to Government employees travelling on duty
Conveyance of mail to China
3,352,670
392,199
1,339,215
Rent for Railway land occupied
by Government departments
127,978
5,212,062
foo
RIES
Conversely, notional debits shown in the accounts consisted of :
Contribution in lieu of rate
Contribution in lieu of duty on
diesel oil used in locomotives
Annual rent charge for use
of Government land
Postage through 0.H.M.S.
$629,208
L
912,651
$ 820,000
$ 1.652
$2,363,511
==
====CE
Furthermore, the salaries of staff include an element for the
cost of fringe benefits, such as pensions etc.
Kowloon-Canton Railway
Balance Sheet as at 31st March, 1977
APPENDIX III
As at 31st March, 1976
Nett Book Value
As at 31st March, 1977
Assets
At Cost
Depreciation to date
$
Nett Book Value
Fixed Assets
2,800,827
Tunnels
3,724,830
1,057,376
2,667,454
1,304,814
Bridges
2,953,594
456,141
2,497,453
129,016
Line Protection
172,024
49,152
122,872
495,994
Telegraphs & Telephones
501,579
29,204
472,375
3,179,202
Tracks
3,379,000
878,953
2,500,047
1,536,854
Signals and Switches
2,259,803
790,464
1,469,339
6,438,214
Buildings
8,498,314
2,226,596
6,271,718
898,325
Plant
2,740,453
1,774,136
966,317
23,989,514
40,772,760
Rolling Stock
58,843,576
83,073,173
30,035.078
37,297,100
28.808.498
45,776,073
Current Assets
Cash
40,893
20,963,211
489,548
73.321
Treasury Current Account Advances and Sundry Debtors
歐
21.566,973
62,339,733
Workshop Manufacturing Account
45,388,683
11,740,288
3.477.156
60,606,127
Current Liabilities
757,878
975.728
Accumulated Funds
Profit and Loss Account Balance as at 1.4.76 Profit for the year
BR
Replacement provision no longer required
abilities
ES
Outstanding payment for the purchase of 40 passenger coaches
1,733,606
62,339,733
Miscellaneous Deposits
41,345
19,522,810
641,984
71.176
20,277,315
66,053,388
57,076,073
4,020,119
61,096,192
3.528,251
64,624,443
500,208
928.737
1.428.945
66,053,388
Notes on the Balance Sheet
Capital expenditure does not include the cost of the new railway terminus at Hung Hom and the value of the land on which it stands, and no provision has been made for compensation to the Railway for surrendering the land and buildings in Tsim Sha Tsui, pending agreement on the financial aspects of the removal of the Kowloon Terminus from Tsim Sha Tsui to Hung Hom with Government.
Under the item "bridges" the nett book value of $27,447 has been written off due to the subsidence of bridge No. 11 at Shing Mun River in August offset by capital expenditure of $1,282,220 on associated emergency work for the bridge.
香港公共圖書館
HONG KONG PUBLIC LIBRARIE
APPENDIX IV
Bar Chart of Revenue Collected from Commuter, Suburban
and International Services for the Year 1976/77
Key:
O
: revenue from international service
$ 00,000
30
: revenue from Suburban service
: revenue from commuter service
28
26
24
22
20
18
16
14
12
10
8
香港公共圖書本
LIBRAR
HONG KONG PUBH"
2
APR MAY JUN JUL AUG SEP
1976
O
OCT NOV
DEC
JAN
FEB
MAR
1977
KOWLOON-CANTON RAILWAY
BUSINESS STATEMENT
FOR THE YEAR ENDED AT 31st MARCH, 1977
APPENDIX V
Profit Centres
Freight Passenger Tenancies Advertising | Other
Total
$
$
$
$
92,894 34,839,595
Revenue :
Specific Costs :
Terminals
15,848,346 15,612,030 1,897,960 1,388,365
754,210 5,288,574
Train operation
856,645 3,731,990
Maintenance of
rolling stock
765,585 4,870,445
Other
Total :
Surplus :
Joint Costs :
Headquarter
administration
Workshop
administration
Permanent way
Structures
Signalling
Departmental
train operation
2,376,440j 13,891,009
6,042,784
4,588,635
5,636,030
51,605
51,605
51,605 16,319,054
18,520,541
13,471,906 1,721,021 1,897,960 1,388,36541,289
KONG PUBLIC LIBRARIE
HONG KONG N
Amortisation
Fayment to
Government
Rent to Govern-
ment
Store charges
Loss on disposal of fixed assets
Total:
Surplus after
deducting
joint costs :
1,304,427
431,191 4,236,325
2,401,529 670,965
43,099 2,688,345
1,541,859
820,000
119,281
243,401
14,500,422
4,020,119
ANALYSIS OF PASSENGER SERVICE
Part I
-
Haulage
APPENDIX VI
1975/76 Revenue
Types of Tickets issued
Current Year (1976/77)
Percentage of
Passenger
Journeys
Passenger Kilometres
Revenue
Passenger
Journeys
Passenger Kilometres
Revenue
2,215,489.30 8,592,717.10
Standard:
First
Ordinary
----
....
....
753,338
6,981,870
18,705,023 142,248,608
2,106,561.05
6.17
7.64
13.49
8,058,408.93
57.18
58.13
51.62
Government:
98.972.60
First
36,253
887,070
105,985.20
0.29
0.36
0.68
209,150.30
Ordinary
....
127,652
3,150,789
187,684.70
1.05
1.29
1.20
Excess Fares:
104,745.98
95,039.02
Passengers travelling without tickets
53,092
1,061,900
106,892.25
0.43
0.43
0.68
Others
****
....
103,116.30
0.66
5,760.00
Golfing Tickets
....
....
300
8,700
960.00
0.01
Monthly Tickets:
(a)
234,164.00
1,070,446.00
First
Ordinary
60,000
....
572,480
1,234,220
10,283,200
157,881.80
0.49
0.51
1.01
654,165.60
4.69
4.20
4.19
4,613,897.00
6-month Scholar Tickets: (a) & (b)
3,626,000
67,153,090
4,068,303.00
29.70
27.44
26.06
(A)17,240,381.30
13,021,020.80 4,219,360.50
(A)17,240, 381.30
-
Total Part I
12,210,985
244,732,600
(B)15,549,958.83
100.00
100.00
99.60
....
....
....
Public
Government
11,805,089.93
....
3,744,868.90 (notional)
(B)15,549, 958.83
1975/76 Revenue
Particulars
39,989.00
6,919.10
46,908.10
Platform Tickets
Air-conditioned Tickets (c) Lavatories
Total Part II
17,287,289.40
Total
Parts I and II
Notes:
Part II
-
Miscellaneous
Current Year (1976/77)
BRARI
Percentage
of
Revenue
Revenue
賻
41,818.50
20,253.00
0.27
0.13
62,071.50
0.40
15,612,030.33
100.00
(a) In relation to monthly and scholar tickets, passenger journeys are based on 40 single journeys per month.
(b) The use of scholar tickets is restricted to Ordinary Class and for journeys on days other than Sundays and Public Holidays. They are not available to stations intermediate between designated stations. (c) Air-conditioned tickets were introduced with effect from 7th February, 1977.
SUMMARY OF PASSENGER TRAFFIC
ӨН
Current Year (1976/77)
APPENDIX VII
Percentage of
Number of
1975/76
Inward
Revenue
Nature of Traffic
. or
Outward
passengers over three
years of age carried
Passenger
Revenue
Kilometres
Number
carried
Passenger
Revenue
Kilometres
1,600,487.10
1,503,119.45
Inward
Bookings to and from Lo Wu
'Outward
801,403
804,572
27,247,702
27,355,448
1,666,855.00
1,642,360.10
6.56
11.13
10.72
6.59
11.18
10.56
6,884,008.36
7,252,766.39
Inward
Bookings to and from Stations other than Lo Wu
17,240,381.30
Total
...
BLIC
5,243,226 93,987,948 6,018,361.68 42.94 Outward 5,361,784 96,141,502 6,222,382.05 43.91
38.40
38.70
39.29
40.02
12,210,985
244,732,600
15,549,958.83 100.00
100.00
100.00
LIBRARIES
書館
1975/76
Revenue
Nature of Goods
ANALYSIS OF GOODS SERVICE
Part I Goods Service (Merchandise and Livestock)
-
Current Year (1976/77)
Charged Weight in Kilograms (Figures within parenthesis indicate actual weight)
Kilogram Milometres F
Revenue
Kilogram
Carried
General Merchandise
Percentage of
Kilogram
APPENDIX VIII
Revenue
Kilometres
9,566,777.75 24,714.65
9,226.95
872.35
Invoiced to and from Lo vu
Inward
1,217,583,750 (646,078,000)
Outward
704,155
704,155)
40,389,703, 300 23,941,270
8,984,328.50 20,283.10
87.79
87.53
0.05
0.05
56.70
0.13
Invoiced to and from stations other than Lo Wu
Inward
342,750
342,750)
8,549,680
6,630.55
0.03
0.02
0.04
Outward
3,150 (
3,150)
51,710
865.15
0.01
Diesel Oil
3,063,540.35
Invoiced from Lo Wu
Inward
168,231,000 (156,994,000)
5,719,854,000
2,043,342.80
12.13
12.40
12.89
1,386,864,805
46,142,099,960
Livestock *
1,898,475.85
14,563,607.90
Invoiced from Lo Wu
Inward
1,641,682 Head
1,553,501.00
9.80
BLJ
12,608,951.10
100.00
100.00
79.57
Part II Goods Service (Miscellaneous)
Current Year (1976/77)
椰
Pevenue
$
1,868,514.03
1975/76
Revenue
1,969,731.93
25,970.75
2,479.90
6,848.75
1,523,765.00
3,528,796.33
18,092,404.23
Particulars
Handling Receipts Baggage and Specie
Parcels
Vehicles and domestic
animals
Postal
Total
-
Part II
Total
Parts I and II
*
IBRARIES
Twenty livestock is approximately equivalent to one ton in weight.
賻
Percentage
of
Revenue
11.79
24,521.45
0.15
1,883.70
0.01
5,260.65
0.03
1,339,215.00
(notional)
8.45
3,239,394.83
20.43
15,848,345.93
100.00
KOWLOON-CANTON RAILWAY INVESTMENT PROGRAMME 1976/77 - 1985/86
3
APPENDIX IX
1
Item (in
order of
priority)
2
Project Description
4
HK m
HKS m
1976/77 1977/78 1978/79 1979/80 1980/81 1981/82 1982/83 1983/84 1984/85 1985/86
HKS m HK$ m HK$ m
HK$ m HK$ m HK$ m HK m
Spread of Expenditure
Total
Invest-
ment
HK m
HK$ m
1
Air-conditioning
of 4 coaches
0.80
0.80
2
Electric induction
heater for retyring
0.09
0.09
Rail Motor Trolley
0.65
0.65
4
Mobile lifting jacks
0.25
0.25
5
Tyre retaining ring
fixing machine
0.18
0.18
6
Wheel lathe
1.23
1.23
7 *
Re-signalling Hung
Hom to Sha Tin
3.50
4.00
7.50
8 *
Lo Wu Marshalling
Yard ($10.71 m)
2.77
3.19
3.19
9.15
9 *
Goods Yard at Fo
Tan ($2.32 m)
1.32
1.00
2.32
10 *
Improvement to
Sheung Shui Station
2.50
11
Additional paving
area at Hung Hom
Terminal ($1.75 m)
0.30
1.45
+ 12 #
Development of Sha
共圖
2.50
1.75
Tin Station
($21.89 m)
12.84
8.36
+ 13 #
Development of Mong
Kok Station
10.00
10.50
1.50
+ 14 @
Beacon Hill Track
Widening (New Tunnel)
13.27
24.97
12.82
0.94
+ 15
Track Maintenance
Equipment
0.13
1.30
1.30
16 *
Re-ballasting of
track
2.40
2.20
2.20
2.20
2.20
21.20
22.00
52.00
2.73
11.20
+ 17
1 locomotive
23.00
+ 18
14 coaches
213.00
2 3.00
$13.00
+ 19 #
Double Track (Sha
Tin Tai Po Market
-
including develop-
ment of stations)
a. Track (including
signals)
b. Station B
9.00
10.00
15.00 10.50
2.50 10.00 10.00
20 *
Sha Tin Racecourse
Station
0.20
5.68
5.68
21
Kwai Chung to Sha
Tin Line
37.00 37.00
37.00
22 @
Shuen Wan Line
35.00
35.00
34.40
BRARIES
}67.
67.00
23 @
Tsim Sha Tsui Line
10.00
40.00
50.00
50.00
+ 24
Hong Lok Yuen
Station
2.00
3.00
11.56
111.00
104.40
150.00
5.00
+ 25 @
Double Track (Tai
Po Market - Lo Wu
including develop-
ment of stations)
4.00
7.00
7.00
7.00
25.00
+ 26 @
Re-signalling for
Double-tracking
(Tai Po Market to
Lo Wu)
8.85
8.85
17.70
+ 27 @
Tai Wai Station
2.00
3.00
5.00
+ 28 @
Fo Tan Station
2.00
3.00
5.00
+ 29 @
Kowloon Tong
Station
0.01
8.35
15.71
3.93
28.00
+ 30 (r)
Electrification
(Kowloon to Lo Wu
cost including
overhead installa-
tion and signal
immunisation)
9.00
9.00 16.00 16.00
+ 31 @
Rolling Stock
(electric)
a. Locomotives (0)
b. Cars (96)
32
Yuen Chau Kok Line
33 @
Tuen Mun
Tai Po
Line ($520 m)
34
Sha Tin Goods Yard
50.00
100.00
100.00
200.00
10.00 70.00 70.00 50,00
200.00
50.00 100.00 100.00 100.00
350.00
(Ma Liu Shui)($10 m)
2.00
2.00
4.59
68.17 107.05 280.53 260.42 326.05 134.40 100.00 100.00 102.00
1,448.81
Freight Traffic for the year 1976-77
Upward (Tonnes
APPENDIX X
Month
Downward (Tonnes
Total
April 76
80
120,532
120,612
May 76
83
94,554
94,637
June 76
63
104,731
104,794
July 76
75
130,328
130,403
August 76
October 76
November 76
September 76
港
44
Nii
48
共
110,030
110,074
5
100,811
100,811
158,5941
158,642
68
141,596
141,664
December 76
96
130,242
130,338
January 77
54
107,308
107,362
February 77
37
85,013
85,050
March 77
59
707
CKONG PUBLIC LIBR
Note: Livestock is excluded from the above table
102,419
102,478
1,386,158
,386,865
APPENDIX XI
Apples
The principle commodities imported from China by rail
7,372 tonnes
Bamboo poles
2,731
"I
Beans
2,465
Bean noodles
Beer
Bleaching powder
1,511 20,586 2,842
"
11
Blankets, cotton
4,155
#1
Bottles
1,016
"
Bran
1,092
Bricks
2,299
"
Candies
2,316
11
Canned goods ...
7,180
11
Cardboard
7,642
Carpet
1,669
"
Caustic soda
2,650
肇
Cement
Chemicals.
Chestnuts
31,281 2,976 2,421
11
*
=
Chillies
1,546
11
Chinaware
Chinese medicine
7,651 9,644
=
"
Clay
3,378
"
Clothing .....
1,489
Commodes
•
2,274
Corn
3,555
"I
Cotton, clothing
8,722
Cotton piece goods
32,303
??
Cotton, raw
Cotton Yarn
•
15,770 13,145 "
#t
Eggs
37,529
"
Eggs, preserved
1,529
Electric appliances
Embroideries
Fish, fresh
Fish, frozen
2,081 2,378 2,056 2,551
11
#1
11
Fodder
2,692
It
Fruits, dried Furniture ..
Garlic, dried Glass sheets
Glassware
Grapes Grease
Ironware
3,443
帽
11,329
..
6,690
"
3,653
11
3,610
#1
2,868
"1
1,123
#
2,730
Iron wire
2,479
11
Line
1,293
"
Maize
1,990
11
Meat, frozen
23,350
"T
Meat, preserved
1,310
=======
Melons
Metal ware
Mineral water
4,360 tonnes
4,314
ย
•
1,410
"I
Newsprint
9,411
Oil, diesel
158,528
Oil, motor, lubrication
2,871
"
Onions
5,349
"1
Oranges
4,854
"
Paper
13,522
"
Paper, toilet
8,058
Peach
8,117
11
Peanuts
•
1,705
Peanut oil
7,387
Pears
Plums
14,047
11
1,119
#1
Potatoes ..
10,224
Poultry (frozen)
11,759
"1
Poultry, live
3,726
#1
Prawns, frozen ....
1,066
10
Pressed wood ........
4,545
"
Roofing felt ..
1,947
11
Rape seed oil
9,557
Safety matches
·
1,305
#1
Salt
2,415
M
Shoes
3,001
Slate
•
2,138
#1
Soap
1,379
Soda
•
Starch
Stationery
1,542
6,366
3,416
Steel bar
14,262
Stones
1,324
Straw matting
1,692
Sundries
100,120
"
Thermos Bottles
1,340
H
Tiles
12,210
11
Timber
5,843
17
Tomatoes
8,541
Towels
2,893
17
Toys
Trunks
Turnips, dried
1,471
11
1,274
1,784
Turnips, fresh
2,507
11
Vegetables, fresh
9,485
Vegetables, preserved
Wine
1,877 6,682
"
803,054 tonnes
ANALYSIS CF TRAIN AND LOCOMOTIVE KILOMETRAGE
(April 1976 March 1977)
-
Appendix XII
Classification
Diesel Electric
Kilometrage
1975-1976 1976-1977 1975-1976
Rail-bus Kilometrage
1976-1977
Passenger
506,217.15508,426.30
1
Train
Goods
182,959.38|156,492.95
Kilometrage
Military Special
Ballast Train
10,469.76
6,640.34 8285
4942
Total Train Kilometrage
699
67
圖
59
8285
4942
Train Kilometrage
Locomotive
Light Locomotive
Kilometrage
699,646.29671,559.59
Shunting Locomotive 50,800.96 36,186.43
Total Locomotive Kilometrage
758,384.46712,606.80
7,937.21
4,860.78
HONG
KÖ
FUEL COST FOR DIESEL ELECTRIC LOCOMOTIVE
(April 1976 - March 1977).
&
PUBLI
RIE
Appendix XIII
Previous Year 1975-1976
$1,572,562.75
Current Year
1976-1977
1.
Total cost of diesel oil for main line running
$1,538,264.97
617.45
$
541.52
2. Average cost per tonne
2,627.3131
3.
Total weight of diesel oil for locomotives (tonnes)
2,626.5623
3.52
4.
Weight per Locomotive Kilometre in Kg.
3.74
CONSUMPTION OF LUBRICANTS FOR LOCOMOTIVES
(April 1976 - March 1977)
Appendix XIV
Previous Year
1975-1976
Current Year
1976-1977
7,704
1.
Total consumption of crank case oil (gallon)
1.016
2.
Consumption per 100 locomotive kilometres in gallons
7,929
1.113
$10.90
3. Average cost of crank case oil for diesel
$10.90
港
electric locomotives per gallon
公
ル
共
ROLLING STOCK
KILOMETRAGE STATISTICS
(April 1976 March 1977)
Appendix XV
館
30.305
Previous Year 1975-1976
$1.386,
HONG
Current Year
1976-1977
1.
Average cost of repair per locomotive Km. (labour and material only)
$1.684
2.
$2.22
3.
Average cost of passenger carriage repair per vehicle km. (labour and material only)
Average cost of diesel fuel per locomotive
$0.331
$2.27
km.
L
$0.1107
4.
Average cost of lubricating oil per loco- motive km.
$0.1213
Engine Number
1
2
4
Engine Type
5
Main Generator
Approximate Weight (Fully Loaded)
Number of Drivers
Fuel Oil
6
7
8
9
10
11
12
13
14
CLASSIFICATION OF ROLLING STOCK
(April 1976 March 1977)
-
Diesel Electric Locomotives
NG KONG
Lubricating Oil
Cooling Water
Sand
Bogie Centres
Driving Wheel Diameter
Bogie Rigid Wheel Base
另外55
53
General Motors
54
G12-1310 H.P.
D12
72 8 770 138
55
12 567C
tons
I.G.
I.G.
170
I.G.
12 cub.
feet
26'-6" 40"
Length over Head Stocks
Height over Rail Level
Width over Handrails
MOTIVE POWER
Appendix XVI
15
16
17
18 19 20
21
22
23
24
*
Gear Ratio
Maximum Permissible Speed
Total Stock at the Beginning of the year
Additions during the year
Reductions during the year
Total Stock at the end of the year
51
General Motors
G12-1125 H.P.
D15
71
8 770
138
170
52
12 567C
tons
I.G. I.G. I.G.
12 cub.
feet
26'-6" 40"
8'-0" 44"-6"
12'-2"
9'-2"
63/14
62
M.P.H.
2
-
2
21 years
& 8
months
39,760
lbs. 25%
Adhesion
28,000
lbs.
56
57
58
Uuu
General Motors
-
G16-1800 P.H. 16 567C
D32
98.3 12 664
tons
166
174.3 12 cub.
37'-0" | 40"
12'2" 56"-8" | 13'-0"
91-3"
63/14 62
3
I.G.
I.G.
I.G.
feet
M.P.H.
8'-0" 441-6" 12'-2" 9'-2"
General Motors
59
G16-1800 H.P.
D32
16
-
567C
98.5 12 625
tons
166
175
I.G.
I.G.
I.G.
12 cub. 37'-0" | 40" feet
12'2" 56"-8" | 13'-0"
9'-3"
63/14
62
M.P.H.
General Motors
60
G26CU-2000 H.P. S32T| 92.1 12 625
16 - 645E
tons
166
I.G. I.G. I.G.
183
6 cub. 32'-
40"
12'2" 51'8" 12'6"
9'-3"
63/14
feet
62
M.P.H.
61
General Motors
G26CU-2000 H.P.D32T|| 98
122
62
16 - 645 E
tons
1000
166
I.G.
183
I.G. I.G.
12 cub.
feet
321
inpo
40"
12-2" 51'8
518 12'6 9-3
63/14
62
M.P.H.
10
Average Age of Class
Maximum Tractive Effort
63/94
62
M.P.H.
3
3
19 years
& 8
months
40.320
lbs. 25%
Adhesion
29,300
lbs.
N
N
1
12
-
3
15 years
& 7
months
66,050
lbs. 30%
Adhesion
50,520
lbs.
1
10 years
& 9
months
66,153
lbs. 30%
Adhesion
50,520
lbs.
3 years
& 1
months
2
1month
50,770
lbs. 25%
Adhesion
54,880
lbs. 25%
Adhesion
50,400
lbs.
50,400
lbs.
Continuous Tractive Effort
CLASSIFICATION OF ROLLING STOCK PRE-WAR CARRIAGES
APPENDIX XVII
(April 1976
-
March 1977)
2
3
4
ל
6
Classification
Average Tare of each Class
Seating
(Ton)
Capacity (Passenger)
Total Stock at
the beginning
of the year
during
the year
the year
Additions
Reductions
during
Ton
Cwt.
Ordinary Class Carriage
38
O
"
38
2
=
"
"
37
1
"
11
35
12
"
11
=
35
12
=
=
35
12
2222222
G PUBLIC
102
1
102
1
102
3
124
1
1
=
"1
=
11
=
35
18
11
35
18
104
Ordinary Class & Brake
38
3
48
Composite Carriage
_
do
36
5
56
Lf
ARIES
Total :
1
14
1
共圖
1
1
1
3
I
7
8
Total Stock at the end of the year
Total Seating Capacity (Passenger)
1
102
1
102
3
306
1
124
124
1
124
1
104
3
312
48
56
14
1402
Classification
AFPENDIX XVIII
2
Average
Tare of
CLASSIFICATION OF ROLLING STOCK
(April 1976
DNOH
each class
Seating
Capacity (Passenger)
G
POST-WAR CARRIAGES
March 1977)
*
4
Total Stock at the beginning
of the year
5
6
Additions
Reductions
during
during the year the year
7
Total Stock
at the end
8
Total Seating
capacity
of the year (Passenger)
Ton
First Class Carriage
42
First Class Carriage
37
First Class Carriage
47
First Class Compartment Carriage
49
Ordinary Class Carriage
44
Ordinary Class Carriage
44
Ordinary Class Carriage
40
PUBLIC
3
72
6
22880
7
7
504
11
68
2
64
3
共
11
880
2
136
3
192
118
10
10
1180
1
118
1
1
118
122
11
11
1342
Ordinary Class Carriage
38
Ordinary Class & Brake Composite Carriage
45
Ordinary Class & Brake Composite
41
19
Carriage
Ordinary Class & Brake Composite
38
5
Carriage
LIBRARES
96
84
65
3
賻
暴
23
23
2208
3
195
5
345
6
504
82
82
7604
====
====
CLASSIFICATION OF ROLLING STOCK
GOODS WAGONS
(April 1976 Merch 1977)
APPENDIX XIX
1
2
3
4
Overall
Average
Carrying
5
Stock
Total Stock at Additions
6
7
8
Classification
Length
of Wagon
Tare of each Wagon Capacity
the beginning.
during
of the year
the year
Keductions
during
the year
at the end of the year
Total Stock
9
Total
Carrying
Capacity
Ton
Cwt.
Ton
Ton
Flat 45 3/4 metric ton
45'-0"
Flat 45 3/4 metric ton
45'- 0"
Flat 80 ton
32' - 0"1
POBL
12
45
10
10
450
19
0
13
#8888
44
1
80
1
共
1
44
Lowsided Open 46 1/10 metric ton
451 O"
-
18
12
45 7/20
10
Lowsided Open 46 1/10 metric ton
40'
011
19
44
1
圖
1
80
10
453 1/2
-
1
44
Highsided Open 45 1/8 metric ton
45'
Covered 44 3/4 metric ton
40'
ᄒᄒ
12
20
Brake Van 10 1/6 metric ton
B°P
મા
44 2/5
20
20
888
35'
O"
19
3
44
10
RI
51
51
2244
5
50
99
4253 1/2
1
Classification
65 Ton Break-down Crane
RB-3 Rail Bus, 6 Cyl. Commer
Capacity: 40 Passengers
Dil Tank Wagon
Length: 41' - 1"
Capacity: 44 1/2 tons
Departmental Carriage:
APPENDIX XX
CLASSIFICATION OF DEPARTMENTAL ROLLING STOCK
(April 1976
March 1977)
Reductions
during
the year
6
Total Stock at the end of the
Year
4
5
2
Average Tare of each
3
Total Stock at◊
Additions
the beginning
during
Class
of the year
the year
Ton
Cwt.
87
Gʻ PUBLIC
5 15
1
21
19
3
No.001 Seating Capacity 60
35
Storage Space - two 16'0"x 9'2"
No.002 Seating Capacity 48
35
Storage Space - one 16'0" x 9'2"
No.003 Seating Capacity 20
38
ARIES
Storage Space - one 16'0" x 9'2"
1
一共圖書本
8
1
3
1
1
8
Tracks
APPENDIX XXI
Items of Minor Civil Engineering Works
The following work was carried out during the year :-
(a) All fishplates were inspected and greased. 649 lengths of
95 lb. F.B. rails, 3,950 timber sleepers and 2,000 cu. yd. of stone ballast were renewed along the mainline.
(b) 860 prs. of fishplates, 2,600 fishbolts, 17,789 dog spikes and
33,200 Macbeth spikes were replaced on the mainline.
(c) 6 sets of 18 ft. switches, 1 set of 15 ft. switches, 7 sets of
1 in 10 crossings, 1 set of 1 in 8 crossing and 700 coach screws were replaced.
共
Formation and line protection
tection
(a) The embankments and cuttings along the mainline were well
maintained. All fouling points and mile stones were repainted.
(b) Earth filling for the diversion of track in connection with
construction of Bridge No. 30 was completed.
Signalling
All point
(a) All signal wires and point mechanism were maintained.
indicators and speed restriction boards were repainted. (b) Signal posts south of Mong Kok Station and south of Sha Tin
Station were resited in connection with double tracking to Sha Tin.
Tunnels
All tunnels were inspected and maintained in good order. All fastenings for the plastic sheet ceiling inside Tunnel No. 2 were checked and repaired, the side channels were also cleared.
Bridges
(a) Bridges No. 4, 5 and 6 were repainted with epoxy resin.
(6)
Bridges No. 31, 24, 35, 20 and 22 were overhauled and repainted with epoxy resin.
(c) Additional fencing was erected at Bridge No. 38.
(a)
Reconstruction of Bridge No. 30 was in progress.
Road level crossings
Road level crossings at Mile 7, 9, 13, 18, 19 and 19% were repaired including renewal of defective fastenings and repacking track.
/Stations
....
Stations
(a) All waiting shelters and/or latrines at Mong Kok, Sha Tin,
University, Tai Po Kau, Tai Po Market, Fanling and Sheung Shui Stations were repainted.
(b) Approach roads at Wo Hop Shek, Fanling and Ho Tung Lau Workshops
were re-surfaced with bituminous material.
(c) Areas at Mile 7 and Ho Tung Lau were filled up with "crusher-run"
to make an unloading yard during the period when Bridge No. 11 was under re-construction.
(d) Approx. 1,500 ft. of P.C. channel covers at Kowloon Station Yard
was replaced with mild steel covers.
(e)
The Running Shed at Hung Hom was overhauled and the open area paved with concrete.
Station Buildings and staff quarters
(a) Station buildings and staff quarters at Tai Po Market, Fanling,
Tai Po Kau and University were repainted and repaired.
(b) A counter was constructed at Lo Wu Station for the China Travel
Service (H.K.) Ltd.
(c) The restaurant counter at Lo Wu was modified and a roller-shutter
installed for a take-away service.
(a)
Staff quarters at Wylie Court were repainted and repaired.
(e) Additional partitions were erected in Rm. 133 in Kowloon Station
for the Traffic Office.
"UBLIC LIBRA
LO WU PASSENGERS
800
17
共
624.142
635,293
775,564
735,889
600
400Z
200
K
336.303
309,522
530.901
479.091
804,936
▼ 786,067
1744.045
804,572|
1801,403
840,884
70/71 71/72 72/73 73/74 74/75 75/76 76/77
PASSENGERS TO CHINA
PASSENGERS FROM CHINA
APPENDIX XXII
CIN MILLIONS >
13
14
APPENDIX XXIII
12-
10-
K
·TOTAL PASSENGERS
共圖書館
LOCAL PASSENGERS
PASSENGERS
CARRIED
3
5
PUBLIC LIBRAR
67/68 68/69 69/70 70/71 71/72 72/73 73/74 74/75 75/76 76/77
FINANCIAL YEARS
GOODS (IN THOUSAND METRIC TONS >
1600
1500-
1400
APPENDIX XXIV
1300
1200
1 100
1000
900
800
700-
600-
500
港公共圖書館
KONG PUBLIC LIBRAR
68/69 69/70 70/71 71/72 72/73 73/74 74/75 75/76 76/77
FINANCIAL YEARS
REVENUE
CIN$┃
MILLIONS)
24-
23
22-
21
20-
19.
18-
17-
16
15
14
13
12
119
10
9
公共圖
港公
-PASSENGER REVENUE
-
8
7
6
5
4
3
2
GOODS REVENUE
NETT PROFIT
LIBRARIES
PUBLIC LIBR
LAUB
68/69 69/70 70/71 71/72 72/73 73/74 74/75 75/76 76/77
FINANCIAL YEARS
APPENDIX XXV
Organization of Kowloon-Canton Railway
(As at 31.3.77)
General Manager
APPENDIX XXVI
Assistant General Manager
Railway Workshops Engineer (In Charge)
Way & Works Engineer (In Charge)}
Assistant General Manager
General
Office
X
|
Way & Works
Development
Training Project Treasury
General
Office
Drawing
Office
Engineer
Engineer
Manager
Manager
Accountant
Departmental Secretary
3
Marketing
Officer
Operating Terminals
Manager Manager
Railway
Stationmasters
Workshops
Engineer
Electrical
Engineer
Way & Works
Inspector
Senior
Clerical
Senior
Clerical
Officer
Officer
.
General
Surveying Drawing
Office
Team
Office
Accounts Pay
Personnel
&
Office Office
General
Registry
Railway Workshop Inspectors
Foreman
Assistant
Way & Works Inspector
Assistant
Way & Works
Running Shed
Locomotive Running Maintenance Carriage Cleaning Power Signals
Maintenance Footplate Staff Train Examiners
Workshops
Carriage & Wagon Repair
Locomotive
Repair
Electrical
Machine
Blacksmith
RA
Inspector
Foreman
Foreman
Welding
Track
Team
Cleaning
ilding
Mechanical
Signals
Foundry
Rigger
Paint
Carpenter
Ticket
Printing
Office
REFERENCE LIBRARY
URBAN COUNCIL PUBLIC LIBRARIES
KWANG
TUNG (CHINA)
YUEN LONG
LO WU STATION
SHEUNG SHUI STATION FANLING STATION
WO HOP SHEK SIDING
PROJECTED LINE TO TAI PO INDUSTRIAL ESTATE (4,43 km.)
LO WU
MARSHALLING
YARD
PROJECTED LINE TO
TUEN MUN (28,18 km.)
UBLIC
TUEN
MUN
LAN
TAO
TAI PO MARKET STATION
TOLO HARBOUR
TAI PO KAU
STATION
UNIVERSITY
HOTUNG LAU WORKSHOPS
PROJECTED SHATIN RACECOURSE STATION
POSSIBLE SECOND LINE THROUGHS LAT
NEW TERRITORIES
STATION
FO TAN SIDING
PROJECTED LINE TO KWAI CHUNG (7.25 km.)
SHATIN
STATION
KHAI CHÚNG
HO MAN TIN SIDING
POSSIBLE UNDERGROUND LINE TO TSIM SHA SHUI
MONG KOK STATION
KOWLOON
IBRARIES
SOUTH
CHINA
HONG KONG
APPENDIX XXVII
в
HOU
LIBRARY
AUTHORITY
LEGEND :-
EXISTING ROUTE PROPOSED ROUTES
SEA
K.C.R. EXISTING & PROPOSED ROUTES
SCALE
250,000
A
ル
共圖
書本
:
352.915(HK)
KOW
1976/77)
Hong Kong. Kowloon
Kowloon - Canton
Railway.
KONG PUBLIC LIBRARIE
Annual
港
恤
書館
ONG KONG PUBLIC LIBRAR
G.PHK
Reprography by the Government Printer, Hong Kong 77200-11L-1/78